After about 10 months from the signing of the EPC contract for the construction of a 72MW Energy Production Plant composed of 4 METAENERGIA WARTSILA 18V50SG gas engines, the construction of the plant is proceeding on time according to the project schedule and in compliance with the rules of the Capacity Market, as defined in the contractual conditions agreed with the Customer. The civil foundations and the steel structures of the main building, that will host the n.4 engines equipped with related auxiliary sistems, have been successfully accomplished, also the foundations of the SCR catalysts, the systems that will reduce the level of nitrogen oxide emisssions in the exhaust gas from the engines.

The engines delivery on site is expected shortly . The commissioning of the plant should take place by June 2023.