The Consortium made by FATA, SIEMENS Energy Global, SIEMENS Energy Italia and DEMONT, has received the official “Notice to Proceed” for the construction of Ostiglia 880MW CCGT power plant in August 2022, after 5 months of Limited Notice to Proceed granted by the Client, where FATA has performed the main design of its scope of work. About more than 50% of overall civil foundations, with pile ramming, have been accomplished; this work progress status includes the full areas will host the GT and ST.
signed the EPC contract for the construction of Ostiglia 880MW CCGT power plant of EP Produzione S.p.A.
The Ostiglia plant falls within the Capacity Market program, at the moment the commissioning of the plant is scheduled for February 2025.