The four Wartsila 18V50SG engines arrived at the port of Termoli by sea were re-assembled and placed in the Engine Hall of the Metaenergia plant.
The mechanical, electrical and instrumentation assembly activities continue, the insulation of the flue gas line is nearing completion and the commissioning activities have begun.
June 20 2023